  • The working process is actively carried out according to plan in Viva Dighomi project
11 December 2020

The working process is actively carried out according to plan in Viva Dighomi project

Recent works

Block A

Completed:

➡️ Roof waterproofing works;

➡️ Facing walls plastering works

In progress:

➡️ Facade paving works to be completed by the end of the month;

➡️ Commercial Floor and Parking Improvement - facing Works

➡️ Paving works for entrance walls, floors and stairwells;

➡️ Water supply and sewerage connection to the external network;

 

Block B.

➡️ Reinforced concrete slab of the roof was laid and thus the main monolithic / concrete construction works were completed;

In progress:

➡️ Facade wall arranging works with bricks;

➡️ Repair works of the partition wall arrangement with blocks;

➡️ Installation of metall-plastic doors and windows on the facade;

➡️ Installation of metal railings on balconies;

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 