Ongoing and completed works  in the 6th and 7th blocks of Viva Rockwell project:

Block # 7

➡️ Reinforced concrete roofing slab of the parking floor was completed

➡️ Waterproofing works of underground floor were completed;

➡️ Arrangement works of the reinforced concrete roof slab of the commercial floor are being completed

Block # 6

➡️ Reinforced concrete slab of the foundation was arranged;

➡️ Installation of reinforced concrete walls and diaphragms of the parking floor has been completed;

➡️ Arranging works of the parking floor roofing tile are in progress;

➡️ A tower crane has been installed and put into operation, which will serve the 7th and 6th blocks