Block 7:
➡️ Reinforced roofing concrete slab of the 10th floor
➡️ Columns, diaphragms and stairs installation works are in progress on 11th floor
➡️ The arrangement of the facade walls with ceramic blocks was completed on the 4th floor;
➡️ Arrangement of interior walls with blocks was completed on the 4th floor;
➡️ The arrangement of metal railings for balconies and loggias was completed on five floors;
Block 6:
➡️ Columns, diaphragms and stairs installation works are in progress on the 9th floor
➡️ Facade brick walls are being arranged - one floor has been completed;
➡️ The interior walls are being arranged in blocks - one floor has been completed;
➡️On the 2nd floor, the installation of metal railings and loggias was completed;