Block 7:
➡️ Columns, diaphragms and stairwells installation works of 10th floor are in progress;
➡️ Internal walls arranging works with building blocks is in progress;
➡️ Facade walls stacking works with ceramic brick have started;
➡️ Metal railings for balconies and loggias are being installing
Block 6:
➡️ Columns, diaphragms and stairwells of the 8th floor are being installing;
➡️ The arrangement works of the inner walls with the building block have started
➡️ Metal railings for balconies and loggias are being installing;
➡️ Facede walls stackingwork with ceramic brick